FY25 Year in review

69%
Salt first construction progress
77%
Pond surface inundation
$935M
Construction cost to date
$347M
Construction spend during FY25
$508M
Estimated cost to complete

Our reports

Our reports

FY25: Milestone year

We proudly transitioned into full-scale operations at Mardie during FY25 – Australia’s largest industrial salt operation and third largest globally. This achievement is the result of years of dedication, technical rigour, and collaborative effort. With operations now underway and confidence in our delivery model, we are firmly focused on progressing toward our next major milestone: first salt on ship to customers during the quarter ending 31 December 2026. This is not just a marker of commercial achievement—it represents the beginning of decades of sustainable supply into global salt markets. As we move forward, BCI remains committed to safe, sustainable operations that deliver enduring benefits for our people, communities, and shareholders.

Operational Progress