FY26 Year in review

85%
Salt first construction progress
49,000t
Crystallised Salt
$1,185M
Construction cost to date
$250M
Construction spend during FY26
$258M
Estimated cost to complete

Our reports

Our reports

FY26: Milestone year

Managing Director, David Boshoff said: “This year, salt crystals formed in our crystallisers, a defining milestone that demonstrated Mardie is now a working salt operation. For me, the moment it became real was holding crystallised Mardie salt in my hands for the first time. After years of planning, construction and pond management, there is no substitute for standing on site with the product itself. It exists, it is here, and it is exactly what we set out to do.”

Operational Progress